EVN steps up efforts to ensure energy infrastructure is ready for APEC 2027

With strong determination and concerted efforts across the organization, Vietnam Electricity (EVN) has accelerated work on power projects to bring them into operation ahead of schedule. At the same time, it has carefully prepared operating and contingency plans to improve the reliability of electricity supply and ensure readiness for major international events, particularly the APEC 2027 Summit.
EVN steps up efforts to ensure energy infrastructure is ready for APEC 2027

The 110 kV Phu Quoc - Bac Phu Quoc transmission line, with a total investment of nearly VND 353 billion, was energized on August 28, 2026. (Source: EVNSPC)

Overcoming challenges to accelerate key projects

Vietnam Electricity (EVN) considers ensuring a safe, stable and reliable electricity supply for the APEC 2027 Summit in Phu Quoc Special Zone a particularly important political task. In recent months, Southern Power Corporation (EVNSPC) has stepped up work on several key power grid infrastructure projects in the special zone.

In August 2026, three projects with a combined investment of nearly VND 2.165 trillion were successfully energized: the 220 kV Phu Quoc Substation, the 110 kV Phu Quoc-Nam Phu Quoc transmission line and the 110 kV Phu Quoc-Bac Phu Quoc transmission line. The projects are intended to increase electricity supply capacity, meet the N-1 reliability criterion and serve both the major international event and Phu Quoc’s long-term development needs.

The greatest challenges arose from land compensation and site clearance. The transmission lines run through residential areas and dense forest. Some plots had changed ownership, while some landowners were absent from the locality, delaying surveys and negotiations. Transporting materials and equipment from the mainland to the island also proved difficult. Heavy rainfall from April 2026 onward significantly affected construction progress. Labor shortages, compounded by the simultaneous implementation of several major projects in Phu Quoc, added to the pressure.

To address these difficulties, EVNSPC proactively sought meetings and working sessions with the An Giang Provincial People’s Committee and the Phu Quoc Special Zone authorities to report obstacles encountered during project implementation. An Giang provincial leaders mobilized the entire political system to work with the power sector to resolve the issues step by step. A steering committee for power projects and works serving APEC 2027 was established, with specific tasks assigned for every tower foundation site and transmission line corridor across all three projects. EVNSPC assigned two Deputy General Directors to oversee work directly at the construction sites, review progress weekly and monthly, and resolve outstanding difficulties and emerging issues in a timely manner, in accordance with the principle of clear responsibilities, clearly assigned tasks and action within the proper authority.

The projects have also received understanding and strong support from local residents. Many households have said they are willing to make part of their land available for power lines, helping provide a safer and more reliable electricity supply for their families and the wider community, while contributing to Phu Quoc’s overall development.

EVN steps up efforts to ensure energy infrastructure is ready for APEC 2027
The power grid continues to expand across Phu Quoc, known as the “Pearl Island”. (Source: EVNSPC)

Recognizing the importance of the projects, EVNSPC instructed the Southern Power Project Management Board, An Giang Power Company and contractors to mobilize all available resources and accelerate construction. Construction crews worked almost every day, making the most of favorable weather to complete each work item. During conductor stringing, contractors used unmanned aerial vehicles (drones) to pull pilot lines across the terrain. This approach helped overcome obstacles posed by dense forest and residential areas, significantly reducing construction time.

Leaders of the Ministry of Industry and Trade, EVN and EVNSPC also made frequent site visits to provide direction, monitor progress and help resolve implementation difficulties. In mid-August 2026, EVN Deputy General Director Nguyen Tai Anh and a delegation inspected the projects, acknowledged the efforts made by the teams and urged them to complete the work ahead of schedule.

EVN steps up efforts to ensure energy infrastructure is ready for APEC 2027

A delegation inspects operations at the 110 kV Phu Quoc Substation on August 17, 2026. (Source: EVN)

Ahead-of-schedule completion lays the groundwork for APEC 2027

Thanks to these concerted efforts, all three projects were completed and energized in August 2026, nearly a year ahead of the overall deadline of September 2027. The 110 kV Phu Quoc–Nam Phu Quoc transmission line was energized in the early hours of August 16, 2026. The 220 kV Phu Quoc Substation was energized at 11:30 p.m. on August 19, 2026, followed by the 110 kV Phu Quoc–Bac Phu Quoc transmission line on August 28, 2026. Completing the projects early leaves more time to test, monitor, adjust and finalize the system, thereby improving operational safety and reliability.

The 220 kV Phu Quoc Substation is equipped with two 250 MVA transformers and connected to a double-circuit 220 kV transmission line approximately 19 km long, including 2.7 km of underground cable. The project has a total investment of VND 877.6 billion. The 110 kV Phu Quoc–Nam Phu Quoc transmission line comprises two circuits, each 20 km long, with 79 tower locations and 2.7 km of underground cable; its total investment is VND 934 billion. The 110 kV Phu Quoc–Bac Phu Quoc transmission line comprises two circuits, each 20.7 km long, with 75 tower locations and a total investment of nearly VND 353 billion.

Once all three projects are in operation, electricity supply capacity across Phu Quoc Special Zone will reach 315 MVA, with scope to increase to 500 MVA. The projects will establish a looped network that meets the N-1 reliability standard and mark an important step in completing Phu Quoc’s power transmission system. They will also help drive socio-economic development in the special zone and ensure a safe, stable and reliable electricity supply for major international events.

EVN and relevant units are looking beyond the timely completion of the projects to ensure that the system is fully prepared for operation. They are developing response scenarios for different types of incidents, plans to prioritize electricity supply, and exercises for the island’s power system. These preparations are designed to ensure coordinated operations and rapid, effective responses in all circumstances, with the highest level of readiness to supply electricity for APEC 2027.

EVN steps up efforts to ensure energy infrastructure is ready for APEC 2027
Caption: Contractors use drones to lay pilot lines, reducing manual work and helping accelerate construction. (Source: EVNSPC)

Alongside its projects in Phu Quoc, EVN is continuing to advance power generation and grid projects across the country. At the Quang Trach Power Center, the Quang Trach I Thermal Power Plant was more than 99% complete overall as of the end of September 2026. Unit 1 had completed test runs at 100% load. On October 20, 2026, EVN held a groundbreaking ceremony for the Quang Trach II LNG-fired Thermal Power Plant and announced that Quang Trach I had been connected to the national grid.

The Tri An Hydropower Expansion Project is also receiving close attention. In the fourth quarter of 2026, the project aims to install more than 2,100 tonnes of equipment, excavate hundreds of thousands of cubic meters of earth and rock, and pour tens of thousands of cubic meters of concrete. The 220 kV substations in An Giang, including Kien Binh, Chau Doc and Rach Gia, have undergone operational checks to help ensure a stable electricity supply to Phu Quoc.

Regarding the power grid, in the first nine months of 2026, EVN and its units started construction on 136 projects (two at 500 kV, 18 at 220 kV and 116 at 110 kV) and energized 131 projects (five at 500 kV, 16 at 220 kV and 110 at 110 kV). In September alone, they started 11 projects and energized 13 grid projects at voltage levels ranging from 110 kV to 500 kV. As for battery energy storage systems (BESS), EVNHANOI has completed 50 MW of capacity, while EVNNPC has completed 155 MW and aims to complete a further 305 MW in October 2026. Power Project Management Board 2 and EVNGENCO 3 are continuing investment procedures for BESS projects in the northern region, with planned capacities of 550 MW and 300 MW, respectively.

EVN continues to work at pace. The Group’s leaders regularly inspect project sites and instruct units to prepare operating plans, contingency measures and response scenarios well in advance. In-depth training in new technologies is also continuing to strengthen staff capabilities.

EVN’s efforts to overcome challenges and complete projects ahead of schedule will not only ensure that the energy infrastructure is ready for APEC 2027, but also provide a solid foundation for the sustainable development of Phu Quoc Special Zone and the national power system in the years ahead. With a strong sense of responsibility, EVN continues to affirm its pivotal role in safeguarding national energy security.

RELATED NEWS
EVN implements comprehensive solutions during intense heatwave
Energy Infrastructure – A foundation for marine economic development
EVN ensures safe, stable power supply in the first half of the year and proactively plans ahead
EVN accelerates projects under adjusted Power Plan VIII: A catalyst for a sustainable economy
EVN's total power output increases by 9.8% in the first 10 months of 2026