Work accelerated on Tan Son Nhat terminal to finish by April next year
Latest
To shorten the schedule and bring Tan Son Nhat aiport's T3 passenger terminal to completion by April 30 next year, the investor and contractors are determined to intensify manpower, machinery, equipment, and construction efforts. (Source: VNA) |
According to Le Khac Hong, the Head of the project Management Board, in order to shorten the schedule and bring the project to completion by April 30 next year, the investor and contractors are determined to intensify manpower, machinery, equipment, and construction efforts.
Currently, the consortium of contractors has mobilised over 400 motorised vehicles and nearly 2,000 engineers and workers, with 80% of the workload finished so far. The construction of various components is underway following the established schedule.
Covering a total construction area of 112,500 sq. m., the terminal is designed to have an annual capacity of 20 million passengers, with a scale of one basement floor and four above-ground ones. It is expected to help double Tan Son Nhat’s operational capacity, thus reducing traffic congestion both inside and outside the currently overloaded airport.